IL&FS to re-launch stake sale process of ITPCL amid restructuring efforts

IL&FS will restart the stake sale process of ITPCL (IL&FS Tamil Nadu Power Co) alongside its ongoing restructuring efforts, with the new IL&FS board seeking to finalise a financial transaction advisor to facilitate the process.

At present, ITPCL is restructuring its debt under the prudential framework for resolution of stressed assets guidelines of June 7, 2019 of RBI for which it has obtained a CRISIL RP-4 rating, with sustainable debt amounting to Rs 4,250 crore. The plan involves segregating the debt into sustainable and unsustainable categories to ensure its viability.

The board had filed an application with the National Company Law Tribunal (NCLT) on January 8, 2021, seeking reliefs for implementing the ITPCLrestructuring plan. However, the NCLT approved some demands but declined others and asked ITPCL to consider the claims of all operational and capital expenditure creditors.

Under the revised plan, 33.16% of admitted claims will be provided to implement the restructuring plan. The operational creditors with finalised settlements are offered 33.16% of their admitted claims over a five-year period upon implementing the ITPCL restructuring plan.

Also, for creditors with conditional settlements, 33.16% of their admitted claims are proposed to be paid. Punjab National Bank, Bank of Baroda, LIC, SBM Bank, SBI, Union Bank of India, PFC Limited are creditors to ITPCL.

An IL&FS spokesperson declined to comment. Earlier, the sustainable debt portion under the restructuring plan ensured 59% recovery for secured consortium lenders. Other financial creditors were to get 30% recovery while operational & capex creditors were offered 15% recovery.

Five capex creditors including China Datang Technologies, Coastal Marine Construction, Sepco III Electric Power, and Shandong Tiejun Electric submitted claims of Rs 608 crore.

NCLT in its order dated July 4, 2022, had observed that “operational creditors/ capex creditors have to be appropriately considered in a fair and reasonable resolution plan” and asked the board to file a supplementary restructuring plan in addition to the debt restructuring plan dealing with claims of operational creditors or capped creditors.

ITPCL, a special purpose vehicle promoted by IL&FS Energy Development Company Limited (IEDCL), is developing a 3180-MW coal-based thermal power plant in Cuddalore, Tamil Nadu. The project is being implemented in phases, with the first phase consisting of a 1200 MW (2×600 MW) power plant. The project’s total cost for the first phase was revised to Rs. 9,116 crore.L&FS in its latest filing has said it has paid lenders 29,000 crore debt as of March 31, 2023 while maintaining overall debt resolution target at 61,000 crore.

For all the latest world News Click Here 

Read original article here

Denial of responsibility! TechAI is an automatic aggregator around the global media. All the content are available free on Internet. We have just arranged it in one platform for educational purpose only. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials on our website, please contact us by email – [email protected]. The content will be deleted within 24 hours.