Delhi-Varanasi Bullet Train UPDATE: Railway Board rejects feasibility report

The proposed Delhi-Varanasi high-speed bullet train project hits a roadblock with the Railway Board rejecting the feasibility report on the project citing multiple curves along the route which will not be suitable for a bullet train to run at 350 kmph. 

The decision was taken at a meeting held by Railway Board Secretary R N Singh last week to review the bullet train project, sources said. The feasibility study report was presented by the National High-Speed Rail Corporation Limited (NHSRCL).

In a statement, the railways, however, said a decision on the feasibility report of the Delhi-Varanasi bullet train project is yet to be taken. “It is hereby informed that no decision has yet been taken on the DPR (detailed project report) of the said bullet train project and the project is still under consideration,” it also said.

Also read: Century-old Delhi Cantonment station to get a revamped look, Indian Railways shares new design

The feasibility report proposed the corridor be built along National Highway-2. Report stated that this will help in the acquisition of land at cheaper rates and reduce the cost of construction.

However, the technical issue which led to the outright rejection of the proposal was that NH-2 had curved sections at many places between Delhi and Varanasi, which would make it highly dangerous for a train to run at 350 kilometers per hour, a source present in the meeting said.

“To run a bullet train at a speed of 350 kmph, the track of the high-speed corridor should be straight,” the source said. While NHSRCL is keen on beginning the work on the project, the Railway Board is wary, especially considering the delays and roadblocks in the ongoing bullet train project between Mumbai and Ahmedabad.

Due to the delays, sources said, the estimated cost of the Mumbai-Ahmedabad project is set to reach Rs 1.50 lakh crore. Officials said around Rs 200 crore is being spent per kilometer to build the high-speed corridor.

The Railway Board has suggested that for now, the focus should be on running only semi-high speed Vade Bharat trains at a speed of 160-200 kmph. Officials said around 400 such trains will be available over the next three years and can be used on different routes.

(With inputs from PTI)

For all the latest business News Click Here 

Read original article here

Denial of responsibility! TechAI is an automatic aggregator around the global media. All the content are available free on Internet. We have just arranged it in one platform for educational purpose only. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials on our website, please contact us by email – [email protected]. The content will be deleted within 24 hours.