364 infrastructure projects show cost overruns of Rs 4.52 lakh crore – Times of India
NEW DELHI: As many as 364 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of more than Rs 4.52 lakh crore, as per an official report.
According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,476 projects, 364 reported cost overruns and as many as 756 projects were delayed.
“Total original cost of implementation of the 1476 projects was Rs 20,84,124.75 crore and their anticipated completion cost is likely to be Rs 25,36,179.03 crore, which reflects overall cost overruns of Rs 4,52,054.28 crore (21.69% of original cost),” the ministry’s latest report for November 2022 said.
According to the report, the expenditure incurred on these projects till November 2022 was Rs 13,67,245.45 crore, or 53.91 per cent of the anticipated cost of the projects.
However, the number of delayed projects decreases to 626 if delay is calculated on the basis of the latest schedule of completion.
Further, it showed that for 456 projects, neither the year of commissioning nor the tentative gestation period has been reported.
Out of the 756 delayed projects, 144 have overall delays in the range of 1-12 months, 117 have been delayed for 13-24 months, 363 projects for 25-60 months and 132 projects have been delayed for 61 months and above.
The average time overrun in these 756 delayed projects is 42 months.
Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.
Delay in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems are among the other reasons.
The report also cited state-wise lockdowns due to COVID-19 (imposed in 2020 and 2021) as a reason for the delay in implementation of these projects.
It has also been observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported, it added.
According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,476 projects, 364 reported cost overruns and as many as 756 projects were delayed.
“Total original cost of implementation of the 1476 projects was Rs 20,84,124.75 crore and their anticipated completion cost is likely to be Rs 25,36,179.03 crore, which reflects overall cost overruns of Rs 4,52,054.28 crore (21.69% of original cost),” the ministry’s latest report for November 2022 said.
According to the report, the expenditure incurred on these projects till November 2022 was Rs 13,67,245.45 crore, or 53.91 per cent of the anticipated cost of the projects.
However, the number of delayed projects decreases to 626 if delay is calculated on the basis of the latest schedule of completion.
Further, it showed that for 456 projects, neither the year of commissioning nor the tentative gestation period has been reported.
Out of the 756 delayed projects, 144 have overall delays in the range of 1-12 months, 117 have been delayed for 13-24 months, 363 projects for 25-60 months and 132 projects have been delayed for 61 months and above.
The average time overrun in these 756 delayed projects is 42 months.
Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.
Delay in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems are among the other reasons.
The report also cited state-wise lockdowns due to COVID-19 (imposed in 2020 and 2021) as a reason for the delay in implementation of these projects.
It has also been observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported, it added.
For all the latest business News Click Here
Denial of responsibility! TechAI is an automatic aggregator around the global media. All the content are available free on Internet. We have just arranged it in one platform for educational purpose only. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials on our website, please contact us by email – [email protected]. The content will be deleted within 24 hours.